A PSDP is appointed by the Client to oversee the coordination of the design work. The PSDP can be either a person or a company, what is important is that the appointed PSDP is able to fulfil the responsibilities of the position. The Regulations require that there be only 1 PSDP appointed for each independent project.
The project supervisor design process must be an individual or body corporate i.e. a limited company. In general, this will be a firm of architects, chartered surveyors, consulting engineers or project managers. It can also be the main contractor (e.g. in cases of design and build contracts or small projects with minimal design input)
A PSDP is appointed by the Client to oversee the coordination of the design work. The PSDP can be either a person or a company, what is important is that the appointed PSDP is able to fulfil the responsibilities of the position. The Regulations require that there be only 1 PSDP appointed for each independent project.
In all cases the person or company undertaking the role must have the necessary competence to carry out the relevant duties. The project supervisor design process must be appointed before design work commences. This is to ensure effectiveness in addressing and co-ordinating safety and health matters from the very early stages of a project.
The PSDP may issue directions to designers or contractors or others.
- Identify hazards arising from the design or from the technical, organisational, planning or time related aspects of the project;
- Where possible, eliminate the hazards or reduce the risks;
- Communicate necessary control measure, design assumptions or remaining risks to the PSCS so they can be dealt with in the safety and health plan;
- Ensure that the work of designers is coordinated to ensure safety;
- Organise co-operation between designers;
- Prepare a written safety and health plan for any project where construction will take more than 500 person days or 30 working days or there is a particular risk and deliver it to the client prior to tender;
- Prepare a safety file for the completed structure and give it to the client;
- Notify the Authority and the client of non-compliance with any written directions issued.